206 Free practice questions for PMP exam

Questions 1-20

c) Preliminary Scope statement

d) None of the above

2) Your construction project was damaged by an earthquake. Your contractor says that he cannot fulfil the terms of the contract due to a specific clause you both had signed in the contract. He is referring to the:

a) Force majeure clause

3) Your vendor has confirmed in writing that he will not be able to provide the products contracted to him, in the time mentioned in the contract. You can terminate the contract and sue for damages. This is a type of:

d) Fundamental breach

4) As a PM, you manage multiple projects. One of your projects is over budget while the other is under budget. You decide to transfer money from the latter to the former and report both projects as within budget. This is against the PMI code of ethics and is called:

a) Unethical management

b) Budget tampering

c) Fraudulent reporting

d) Cost leveling

5) Y our brother can influence bids in the vendor company that has been contracted for your project. You should:

a) Disclose the bid price that is most likely to make him win

b) Reject other vendors and award him the contract

c) Refrain from the decision-making process and make a full disclosure to stakeholders and wait for their decision before you proceed

d) Pretend during meetings that you don't know your brother

6) A project you are managing is about to be completed. But there is a minor defect in the work produced by the contractor. You should:

a) Neglect the defect if it is trivial

b) Ask the contractor to fix according to SOW

c) Submit a change request

d) None of the above

7) As a PM, you have identified some low priority risks. You should:

Source

Related Posts:

  • Invention Services For InventorsInvention Services For Inventors What Does InventHelp Do? InventHelp Attends Trade Shows InventHelp attends a number of trade shows where it uses pro… Read More
  • Prilosec OTC IngredientsPrilosec OTC Ingredients Last Updated: Mar 18, 2011 | By Stephanie Chandler Prilosec OTC is an over-the-counter medication for the treatment of hear… Read More
  • Cuddle Bed 400-ThreadCuddle Bed 400-Thread-Count Mattress Topper About this item The Cuddle Bed 400-Thread-Count Mattress Topper feels as soft as it looks. A quilted side … Read More
  • Ichimoku CloudIchimoku Cloud DEFINITION of 'Ichimoku Cloud' A chart used in technical analysis that shows support and resistance, and momentum and trend directions … Read More
  • Cystic AcneUnderstanding Cystic Acne and Nodulocystic Acne Photo ©, A.D.A.M. Updated December 20, 2014. Written or reviewed by a board-certified physician. S… Read More

0 comments:

Post a Comment